Tuesday, 29 October 2013

Estimate Cost Process

Estimate Cost
Once the scope is baselined in terms of deciding the project boundaries and also, as soon as the schedule is baselined in terms of coming up with the schedule with details about the activities, their duration and the resource requirements, one of the next steps is to come up with the cost estimate.

Prior to coming up with the cost estimate, it is necessary to have a plan as as to how the estimation process will be covered.

Based on the above understanding, here are the inputs to the estimate cost process:
1. Scope baseline: What is the boundary to be covered.
2. Schedule baseline: The schedule having details about the activities, their duration and the resource count for each activity.
3. Human Resource Management Plan: While the resource count gets covered in the project schedule, the resource characteristics,personnel rates gets covered in human resource management plan.
4. Cost Management Plan: How to estimate the cost for this project, what tools to use?

Generally, PM plan can be taken as an input (to cover all of the above) since it has the different baselines and plans too but , to be specific and vital, specific inputs like, scope and schedule baselines are listed as inputs.

Going ahead, the following are other inputs,

5. Enterprise Environmental Factors - Cost estimation can have external factors like, government approval, license cost etc. to be considered
6. Organizational Process Assets - For  leveraging any prior experience or template reuse because this is a vital process and it is necessary to follow  a process and reuse prior experience as much.
7. Risk Register - what risks need to be accounted (contingencies cost)

Cost estimation is understandably a vital process and so, it needs experience in terms of anticipating all issues and covering those in the estimate. Looking at the scope and schedule baselines, the cost is estimated for the project activities. Not all the times there is enough information to do the estimate. So, different types of estimation techniques need to be followed based on experience. Personnel rates are applied alongwith activity duration and resource count to come up with the cost estimate, first at activity level , summing it up to the project level using a project management software. Estimation for any risks is also an important aspect since it helps add a buffer to the actvities and the project as such. Different types of estimation techniques like top-down approach, bottom-up estimation are used. Cost of conformance and non-conformance in terms of quality is also an important aspect to be covered. All these are added on to a project management software like Microsoft Project Plan (MPP).

Based on the above understanding, here are the tools and techniques:
Project Management Software - for activity-wise cost estimation and cumulation
Different estimation techniques: based on available information, different techniques might be used:
 1. Bottom-Up estimation - results in more accurate estimates since the estimator knows what time it takes to complete each activity since he/she has done something like this before
 2. Top-Down or Analogous estimation - based on experience or comparison with other projects a high-level estimation is arrived at. Here accuracy may not be there but if this is coupled with experience then a good estimate can be arrived at. Mostly this estimate has a range.
 3. Parametric estimation - if the model is good, can result in accurate estimates. e.g., rate / sq ft multiplied with no. of sq ft to come up with the cost for the land as a whole.
 4. Three-point estimating: Optimistic, most likely and pessimistic estimates used to come up with the actual estimate for the activity.

Based on the  understanding of the process, the following are generally important techniques for this process -
Expert Judgment
Analytical Techniques like brainstorming, delphi technique are used

Apart from the above, the other techniques used are -
Cost of Quality: Cost of conformance and cost of non-conformance
Reserve Analysis: What amount of reserve is needed to account for known and unknown risks. They are usually a percentage of the estimate.
Vendor bid analysis: Based on what is the bid rate, the actual project cost can be benchmarked and then estimated.

Outputs:
Proj Document Updates: There might be a need to add missing information (onto other project documents) uncovered as a result of this process.
Activity Cost Estimates: For each activity what is the cost, based on no. of resources used and the duration for which they are used alongwith the personnel or resource rate for the concerned resources.
Basis of Estimates: On what basis this estimate was arrived at. Any supporting documents, attributes to support the estimation process and make it reliable.


Visit http://pm-prep35.com/ittolaunchpage.aspx

Monday, 28 October 2013

Plan Cost Management

Plan Cost Management
Once the project charter charter is received, the project manager builds a PM plan outline. As he does that, he starts building the core of the PM Plan - The core objectives being the scope, time and cost. So, the scope, time and cost management plans are built in an iterative manner - looking up one while building another and filling information in the relevant plans.

As with any plan, these plans will have information about what processes are relevant in the knowledge area for the project and also add any tailoring guidelines for the different documents in the concerned knowledge area. The plan documents leverage prior experience in the organization rather than thinking right from scratch. So, all tools and techniques to leverage experience is utilized by the manager.

The Plan Cost management process deals with coming up with a process to derive the cost baseline, manage cost baseline and changes to the baseline. It also deals with defining process tailoring guidelines for the other processes in this knowledge area based on the project context. It also has details about the estimate like the unit of measure, range, accuracy etc.

Inputs:
Project management Plan: As in case of all other processes and also since planning is an iterative process and project management plan is one of the first documents the project manager starts outlining, the contents in the project management plan are useful in detailing the cost management plan.
Project Charter: Since scope , time and cost are termed triple constraints and they are the first few knowledge areas whose plans are detailed, project charter becomes an important input to take care of risks, assumptions and constraints and also the high-level budget allocated in case of the cost management process.
Enterprise Environmental Factors: As with all planning processes, the effect on project due to external factors becomes an important input for the planning process and that too in case of the planning processes part of triple constraints.
Organizational Process Assets: The templates and prior experience is leveraged to build the cost management plan.


Tools and Techniques:
Expert Judgment: Expert Judgment from experienced managers and consultants is leveraged to create a viable cost management plan.
Analytical Techniques: Analytical techniques like brainstorming, delphi technique become handy in detailing all possible scenarios and building the plan for the same.
Meetings: A lot of time in spent by the project manager in meetings during the planning phase. So, this is an important tool that a manager must utilize.

Outputs:
Cost Mgmt Plan: Has details about how cost will be managed within the provided budget. The plan keeps in mind about other objectives and provides a feasible plan to manage cost. Some of the factors covered in the cost management plan are -
- Units of measure
- Order of magnitude (range)
- Rules and frequency for performance measurement



Visit http://pm-prep35.com/ittolaunchpage.aspx

Friday, 25 October 2013

pm-prep35 Toppers List Update


Good to see chapter tests getting filled with toppers list -

Chapter-1 and Chapter-2:   >90% scorer:
pm-prep35 Chapter-1 Toppers List



Chapter-2 Toppers List
These chapters seem to be among the tougher ones. The pass percentage is too low for these two chapters. Being the first two chapters, it is among  the first everyone starts studying but maybe the test has got better off in this case.

Chapter-3 ,Chapter-4 ,Chapter-5, Chapter-6, Chapter-11: No toppers yet
Chapter-4 Toppers List
Chapter-5 Toppers

Chapter-3 Toppers List




Being one of the main chapters any PMP aspirant would like to be thorough with, not any passers in these chapters, although there have been takers.

Chapter-7 Toppers List:


Takers seem to believe in taking their time to prepare. This seems to be a consistent pattern across the different tests and takers seem to return after a brief period of preparation. 

Chapter-8 Toppers List:

The one and only 100% scorer that too in the very first attempt. Important to note that this doesn't have many passers although it has had many takers -



Chapter-10 Toppers List:

Some of the takers are regular -

Chapter-10 Toppers List

Chapter-13 Toppers List:


Some of the takers seem to enjoy the test while others use it to check their consistency. Chapter-13 test seems to be favorite among takers at the moment.




Manage Stakeholder Engagement

Here is the gist about this process:

- Addressing the different stakeholder needs
- Ensure Stakeholders stay communicated at the planned milestones and at any vital points as planned
- Ensure methods or modes of communications are followed as stated in the communication management plan
- Track issues and update the stakeholders on a regular basis
- Communicate change requests status in change log
- Track changes and raise appropriate change requests for input to ICC process
- Update OPA with lessons learnt or any process tailoring / optimization details
- Ensure PMP stays updated due to changes in timeline or cost due to new issues
- Use communication techniques like negotiation and people management effectively to increase chances of project success

Based on the above gist, here are the inputs, tools and techniques and outputs:

Inputs
Stakeholder Management Plan
Commmunications Management Plan
Change Log
Organizational Process Assets

Tools and Techniques
Communication Skills
Interpersonal Skills
Management Skills

Outputs
Issue Log
Change Requests
OPA updates
PMP Updates
PD Updates

 Refer http://pm-prep35.com/ittolaunchpage.aspx

Plan Stakeholder Management

The Plan Stakeholder management process is concerned with coming up with the stakeholder management plan - how different project stakeholders, identified as part of initiating process, will be handled. The idea here is to ensure that all types of stakeholders are thought over and covered in order to have a viable approach to handle their needs.

Based on the same, here are the inputs:

Project Management Plan: As with all of the planning processes, this is a general input in terms of the fact that the project manager usually starts with an outline plan and develops more specific plans, relevant to each knowledge area.
Stakeholder Register: An output from the Identify Stakeholders - initiating process that has the list of stakeholders who need to be taken care in terms of ensuring that their objectives are prime to the project success.
Organizational Process Assets: As will all planning processes, this is an important input to look at lessons learnt, processes followed so far, tailoring guidelines etc.
Enterprise Environmental Factors: Another vital input for all the planning processes. Since planning mainly needs to account for external factors affecting the project.


Here are the tools and techniques:

Expert Judgment: The general technique applied in case of planning processes because it is necessary to leverage consultant and senior manager view point here to ensure that the project is covered of all aspects.
Meetings: Lot of time is spent on meetings during the planning phase since it is necessary to take the input from various quarters during the planning phase.
Analytical Techniques: A usual technique used when developing the plan. The current engagement level and desired engagement level are analyzed. The following are the different engagement levels of the stakeholders:

Unaware: Unaware of project and potential impacts. Needs utmost guidance.
Resistant: aware of project and potential impacts but resistant to change. Mostly tough to handle.
Neutral: aware of project and potential impacts but neutral to change. Can be influenced with proper facts.
Leading: aware of project and potential impacts. Proactive in ensuring that the project is a success. Easy to work with.

Here are the outputs:
1. Stakeholder management Plan: Has details about how to handle different group of project stakeholders, current and desired engagement levels, communication requirements and communication points, general process as to what other processes in stakeholder management knowledge are applicable and how they will be tailored to the current context, how changes will be handled.
2. Project Document Updates: Updates to other documents as management plan is developed.


Although not stated in the PMBOK, project management plan updates can also be an output to this process.

Visit http://pm-prep35.com/ittolaunchpage.aspx

Project Stakeholder Management - Introduction

While Project Human Resource Management is concerned with assigning the project team , training the team and ensure that their performance stays appraised, the project stakeholder management is concerned with not only with the project team but generally people influencing the project. The stakeholders might be the customers or contractors or project team's family members.

Here are the processes falling in this knowledge area:
1. Identify Stakeholders
2. Plan Stakeholder Management
3. Manage Stakeholder Engagement
4. Control Stakeholder Engagement

Based on these processes, the stakeholder management knowledge are has the following responsibilities:

1. The project stakeholders are identitied initially in order to ensure that their requirements are accounted during the requirement collection process.
2. Once the stakeholders are identified and the gamut of stakeholders is known, then how they will be managed will help in having having a plan on hand. Planning might involve at what points they will be contacted, what sort of communication model will be followed for the different categories of stakeholders are some of the things to be planned.
3. Once a plan is in place, the next step is to ensure that the plan is executed at the appropriate phase or point in the project lifecycle.
4. Control Stakeholder Engagement is concerned with coming up with corrective or preventive actions if there is any deviation from the plan or there needs to be a change in approach in dealing with the stakeholders.

Stakeholders can have a positive or negative impact on the project objectives. As a project manager, it is important to influence factors that case positive impacts while reducing the effect of negative impacts. This is what differentiates project success from failure.

Visit http://pm-prep35.com/ittolaunchpage.aspx

Control Schedule Process

The Control Schedule process is concerned with -
1. Ensuring that changes are processed in a controlled manner.
2. What has been accomplished so far and what is yet to be accomplished.
3. Ensuring that changes are properly managed.
4. Ensuring that the schedule will be under control in future as the project progresses
5. Ensuring that the project schedule is covered for all possible impacts
6. Ensuring that the schedule data (actuals) collected in the schedule model is correct
7. The availability of resources in case if schedule goes out of control
8. Ensuring critical path and buffers are under control
9. Incorporating changes to the baseline once change is approved by the change control board

In an agile approach, control schedule process might also cover -
1. Work re-prioritization
2. Determine the work velocity in a given iteration and ensure everything stays controlled

The common inputs to this process are:
1. Project management plan: This is the baseline document against which helps in deciding if corrective action is required and impacts to other constraints.
2. Work performance data: The common monitoring and controlling  process input coming from the executing process to cross-check if the schedule is under control.
project schedule: This gives an idea of what has been accomplished and what is planned ahead and if the schedule is under conrtol.
3. Project calendars: In case if schedule is not under control , then there might be a need to plan for corrective action in which case, project calendars of the resources need to be looked up to bring the schedule under control.
4. Schedule data: What has been collated in the form of actual dates and resource allocations will be checked and ensured to be correct.
5. Organizational process assets: Reporting methods , policies for schedule control etc.

The tools and techniques part of this process are:
1. Performance reviews: How is the schedule performing and will perform - forecasts. Here are some of the review techniques:
- Trend Analysis: Based on current performance, what will be the future and if everything will be under control at a later point.
- Critical Path Method: What mileage has been covered in the critical path will give a better idea of the project health and corrective / preventive actions needed.
- Critical Chain Method: What amount of buffer was allocated and what is used will give an idea of a need for corrective actions
- Earned Value Management: Schedule Variance (planned v/s actual), schedule performance indicator to check the health of the project and decide on corrective actions.
2. Project Management Software: Softwares like Microsoft Project Plan are useful in looking and understanding the schedule data and finding variance / trends and then useful in finding if there will be a need for corrective action.
3. Resource Optimization Techniques: How effectively resources can be used to get the schedule under control.
4. Modeling Techniques: They are used to simulate what-if scenarios affecting the project objectives and seeing the impacts to the schedule.
5. Leads and Lags: Leads and lags can facilitate paralleling of activities and thus help in gaining time-saving or schedule time gain or schedule catchup.
6. Schedule Compression: Adding more resources if schedule is lagging behind, in order to get schedule back on track.
7. Scheduling Tool: Usually part of the project management software, the scheduling tool is used to build the network diagrams and do some base work that can be looked up and corrected if needed.

The outputs from this process are:
1. Work Performance Information: The data is made concise good for reporting or to be fed in the change requests and then to be presented before the change control board.'
2. Change Requests: The document holding the changes and their impacts to different project objectives like cost and schedule impact. This becomes the input to the integrated change control process.
3. Organizational Process Assets Update: Any new lessons learnt or process tailoring guidelines become part of the organizational process assets.
4. Schedule Forecasts: These become inputs to the integrated change control process.
5. Project management plan updates: Changes to Schedule baseline, once changes are approved by the change control board.
6. Project Document Updates: Any updates to other documents like risk register or other relevant documents based on the change.

Visit http://pm-prep35.com/ittolaunchpage.aspx