Wednesday, 11 September 2013

Define Activities - PMBOK® Guide – Fifth Edition


6.2 Define Activities
Define Activities
Define Activities Process:
The Define Activities process is concerned with decomposing the Work package into a list of relevant activities. In most of the projects, the Create WBS and Define Activities are done as part of the same process. In order to create a WBS that covers all the work packages within the scope, the whole team must be involved in the process. It is natural from there for the team to breakdown to the initial activity list. Also, when the project manager actually starts with the project schedule, the starts with the preliminary activity list and then goes onto relate those (with a project management software like MPP),  allocates, durations for each of the activities along with the resources to come up with a detailed schedule. So, most of the processes in the schedule management knowledge area overlap without distinct demarcation.


Define Activities Process - Introduction

Inputs:
1. Schedule Management Plan: The Schedule Management Plan has the process to decompose the WBS to an activity list relevant to the project objectives.
2. Scope baseline: The Scope baseline covers the scope statement, scope management plan and WBS. When coming up with the activity list, it is good to keep in mind what is the scope and the baseline is a good input to that effect.
3. Enterprise Environmental Factors: For all the planning processes, enterprise environmental factors are a vital input since the planning phase needs to factor the proper conditions under which work will be carried out.
4. Organizational Process Assets: Initial Process outline, process tailoring guidelines for this customer, context.

Define Activities Process Inputs

Tools & Techniques:
1. Expert Judgment: Expert opinion from team and SMEs is very important in order to define activities.
2. Decomposition: Breaking down the work package to one or more activities, while work package is assigned to a team , the activities are allocated to individual resources.
3. Roll Wave Planning: When the WBS is broken down to work packages and then the individual work packages are broken down to activities, not all of the work packages in the WBS are broken down, only work packages relevant to current project phase are broken down keeping the other deliverables at the high-level. This process is called roll wave planning. Plan what you want to execute in the coming next period say, a week or two.


Define Activities Process Tools & Techniques

Outputs:
1. Activity List: It is a list of activities for a work package. Each individual activity has an activity identifier and an activity description. 
2. Activity Attributes: Any further details useful while developing the schedule can be part of activity attributes -  any unique characteristics for each of the activity gets added as activity attributes.
3. Milestone List: While activities have durations attached during estimate activity duration process, milestones are pre-marked or they have zero duration. They are mostly delivery-related and are checkpoints.

Define Activities Process Outputs

Define Activities Process - Match the Following

Define Activities Process - Match the Following (Answers)
http://pm-prep35.com/launchdefactvtsittotxt.aspx

Visit http://pm-prep35.com/timelaunchpage.aspx
- First-Ever Completely Free Online Contact Hours for PMP Exam

Sunday, 8 September 2013

Plan Schedule Management - PMBOK® Guide – Fifth Edition

6.1 Plan Schedule Management

The Plan Schedule Management Process is concerned with creating the schedule management plan. The schedule management plan is concerned with keeping the project schedule managed, monitored and controlled, in case of any changes to schedule.


6.1 Plan Schedule Management

The Plan Schedule Management Process has the "process" for -

1. Decomposing the WBS to an activity list. 
2. Documenting the activity interrelationships in the form of a network diagram.
3. Doing activity resource estimates.
4. Doing activity duration estimates.
5. Developing the detailed schedule
6. Controlling Schedule in case if there is a variance

The tools and techniques for the different schedule processes are also decided and documented in the schedule management plan looking at the project constraints and the competing objectives.

Plan Schedule Management - Introduction
Inputs:
1, PM Plan: The Project Management Plan is an important input to the plan schedule management process because, planning by itself is an iterative process. The PM Plan mostly starts with an outline for each section  and then, each of the sections get elaborated into a detailed subsidiary plan as the project planning gains momentum.
So, the subsidiary plans are an input to develop project management plan process and PM Plan is a vital input to each of the subsidiary plans.
2. Project Charter: The Project Charter is the most detailed document when the project enters the planning phase. It also has the high-level details with respect to all the knowledge areas. This is where it becomes a reference document in the first few iterations of project planning.
3. Enterprise Environmental Factors: What are the external factors influencing the project? Is the project being done by a virtual team? Are there are labor unions in the organization? What positive or negative impacts can the external environment have on the project?
Plan Schedule Management - Inputs - Part 1
4. Organizational Process Assets: Templates are very important input in the first iteration of planning. What is the process followed so far in coming up with a plan in previous similar projects?
Plan Schedule Management - Inputs - Part 2
Tools and Techniques:
1. Expert Judgment: Opinions from experienced managers or SMEs in similar projects are taken into account while detailing the plan.
2. Analytical Techniques: Brainstorming , delphi technique or taking surveys / polls and any other techniques relevant to collecting facts , data or opinions to analyze and come up with a well derived plan.
3. Meetings: The SMEs and the PM spend time in meetings during planning to walk through all objectives, gather opinions and come up with the best approach relevant to the project.
Plan Schedule Management - Tools & Techniques

Outputs:
The Schedule Management Plan is the output from Plan Schedule Management process and it has the details about how other processes within the Project Time Management Knowledge area will be performed and also how they will be monitored and controlled once the baseline is approved.
Plan Schedule Management -  Outputs

Plan Schedule Management - Match the following

Plan Schedule Management - Match the following (Answers)